Types of bill of quantities
Contents |
[edit] Introduction
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor) that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers for them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are two types of bill of quantities; firm and approximate.
[edit] Firm bill of quantities
A firm bill of quantities is used to obtain a lump-sum price for a fully-designed project. The work required is measured and described precisely, meaning that it can be priced accurately. As a result, tender prices should be reliable and good financial control should be possible. Where changes are necessary to the works described in the tender documents, the bill of quantities provides a good basis for assessing the costs of those changes.
[edit] Approximate bill of quantities
An approximate bill of quantities (sometimes referred to as a notional bill of quantities or provisional bill of quantities) is subject to re-measurement, and is used if there is insufficient information to prepare a firm bill of quantities at the tender stage, or if it is decided that a firm bill of quantities is not necessary.
The description of the works required is complete, but the quantities are approximate. As a result, quantified schedule of rates are provided by tenders rather than a lump-sum price, and the quantities are subject to re-measurement on completion.
This may appear an attractive option, as less cost and time is required to prepare the bill of quantities, however, typically, there will be more variations, and as re-measurement is required, overall administrative costs may be higher. In addition, there is greater cost uncertainty.
See also: Bill of quantities breakdown structures for descriptions of the three main breakdown structures for bills of quantities:
NB: An 'unpriced bill of quantities' (sometimes referred to as the tender pricing document) is the document issued to tenderers, who will then estimate their price for each item. The 'priced bill of quantities' constitutes the tenderer's offer and is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Without quantities.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.